Energy Transition Program: Three Public Institutions to Benefit from Solar Power Installation
As part of the ongoing implementation of the energy transition program within public institutions, three institutions will benefit from the installation of photovoltaic systems for electricity production from solar energy, intended for self-consumption and the realization of projects aimed at improving energy efficiency in public buildings under these institutions. The objective is to reduce energy demand and decrease state subsidies allocated to energy materials.
This decision was published in the Official Journal on November 27, 2025.
Program Overview
The energy transition program in public institutions refers to the "photovoltaic grid-connected" program and the "Energy Efficiency Program in Public Buildings," each subject to a separate loan agreement between the Tunisian Republic and the German Development Bank (KfW), or a combination of both.
Institutions Benefiting from the Program
The program concerns institutions under the Presidency of the Government and the Ministry of Transport, namely:
- The Official Printing Press of the Tunisian Republic in Ben Arous
- The Civil Aviation and Airports Office (OACA) in Tozeur
- The building of the Presidency of the Government in Bab Al Assal, Tunis
Program Funding and Implementation
The estimated cost of this phase of the program is 13 million dinars, financed by a loan and a grant from the German Development Bank (KfW) as well as credits from the Energy Transition Fund. The National Agency for Energy Management (ANME) is responsible for pursuing the execution of the program as a delegated project owner, in accordance with the conditions and procedures stipulated in the two separate conventions, according to the text of the decree published in the Official Journal.
Program Timeline
The duration of the program is set at six months from the date of publication of this joint decree in the Official Journal of the Tunisian Republic.